Information Technology Project Management 9th Edition by Kathy Schwalbe Test bank

分享 时间: 加入收藏 我要投稿 点赞

 c. Project time management d. Project cost management 
 
ANSWER:  b
RATIONALE:  Feedback: Project management knowledge areas describe the key competencies that project managers must develop. Project scope management involves defining and managing all the work required to complete the project successfully.
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.11
QUESTION TYPE:  Multiple Choice
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.3 - LO: 1-3
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  What is Project Management?
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  5/7/2018 6:38 PM
 
36. Which project management knowledge area ensures that the project will satisfy the stated or implied needs for which it was undertaken?
 a. Project cost management  b. Project time management 
 c. Project risk management  d. Project quality management 
 
ANSWER:  d
RATIONALE:  Feedback: Project management knowledge areas describe the key competencies that project managers must develop. Project quality management ensures that the project will satisfy the stated or implied needs for which it was undertaken.
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.11
QUESTION TYPE:  Multiple Choice
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.3 - LO: 1-3
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  What is Project Management?
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  5/7/2018 6:48 PM
 
37. Which project management knowledge area primarily involves generating, collecting, disseminating, and storing project information?
 a. Project cost managementb. Project procurement management
 c. Project time managementd. Project communications management
 
ANSWER:  d
RATIONALE:  Feedback: Project management knowledge areas describe the key competencies that project managers must develop. Project communications management involves generating, collecting, disseminating, and storing project information.
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.11
QUESTION TYPE:  Multiple Choice
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.3 - LO: 1-3
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  What is Project Management?
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  5/8/2018 10:50 AM
 
38. Project procurement management mainly involves:
 a. making effective use of the people involved with the project.
 b. buying goods and services for a project from outside the performing organization.
 c. generating, collecting, disseminating, and storing project information.
 d. identifying and analyzing stakeholder
needs while managing and controlling their engagement.
 
ANSWER:  b
RATIONALE:  Feedback: Project management knowledge areas describe the key competencies that project managers must develop. Project procurement management involves acquiring or procuring goods and services for a project from outside the performing organization.
POINTS:  1
DIFFICULTY:  Difficult: Moderate
REFERENCES:  p.12
QUESTION TYPE:  Multiple Choice
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.3 - LO: 1-3
NATIONAL STANDARDS:  United States - BUSPROG: Analytic
TOPICS:  What is Project Management?
KEYWORDS:  Bloom's: Comprehension
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  4/27/2018 2:53 PM
 
39. Which project management knowledge area is an overarching function that affects and is affected by the different knowledge areas?
 a. Project cost managementb. Project stakeholder management
 c. Project integration managementd. Project communications management
 
ANSWER:  c
RATIONALE:  Feedback: Project management knowledge areas describe the key competencies that project managers must develop. Project integration management is an overarching function that affects and is affected by all of the other knowledge areas.