Information Technology Project Management, Revised 7th edition by Kathy Schwalbe Test bank
KEY: Bloom's: Knowledge
3. _____ refers to work done in organizations to sustain the business.
ANS: Operations
PTS: 1 DIF: Difficulty: Easy REF: p.4
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Knowledge
4. _____ include people, hardware, software, or other assets.
ANS: Resources
PTS: 1 DIF: Difficulty: Easy REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Technology TOP: What is a Project?
KEY: Bloom's: Knowledge
5. A project’s sponsor is also known as a(n) _____.
ANS: primary customer
PTS: 1 DIF: Difficulty: Easy REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Knowledge
6. In project management, the three limitations of scope, time, and cost are referred to as the _____.
ANS: triple constraint
PTS: 1 DIF: Difficulty: Easy REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Technology TOP: What is a Project?
KEY: Bloom's: Knowledge
7. The question, “What unique product does the customer expect from the project?” is an example of a(n) _____ constraint.
ANS: scope
PTS: 1 DIF: Difficulty: Moderate REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension
8. The question, “What is the project’s schedule?” is an example of a(n) _____ constraint.
ANS: time
PTS: 1 DIF: Difficulty: Moderate REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Product?