KEY: Bloom's: Comprehension
9. “What is the project’s budget?” This is an example of a project’s _____ constraint.
ANS: cost
PTS: 1 DIF: Difficulty: Easy REF: p.8
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Product?
KEY: Bloom's: Knowledge
10. The _____ of project management includes quality, scope, time, and cost constraints.
ANS: quadruple constraint
PTS: 1 DIF: Difficulty: Easy REF: p.9
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Knowledge
11. _____ is “the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.”
ANS: Project management
PTS: 1 DIF: Difficulty: Easy REF: p.9
OBJ: LO: 1-3 NAT: BUSPROG: Technology
TOP: What is Project Management? KEY: Bloom's: Knowledge
12. Project management _____ describe the key competencies that project managers must develop.
ANS: knowledge areas
PTS: 1 DIF: Difficulty: Easy REF: p.11
OBJ: LO: 1-3 NAT: BUSPROG: Technology
TOP: What is Project Management? KEY: Bloom's: Knowledge
13. Project _____ management includes estimating how long it will take to complete work, develop an acceptable project schedule, and ensure timely completion of a project.
ANS: time
PTS: 1 DIF: Difficulty: Moderate REF: p.11
OBJ: LO: 1-3 NAT: BUSPROG: Technology
TOP: What is Project Management? KEY: Bloom's: Comprehension
14. Project _____ management consists of preparing and managing the budget for a project.
ANS: cost
PTS: 1 DIF: Difficulty: Moderate REF: p.12