Information Technology Project Management, Revised 7th edition by Kathy Schwalbe Test bank

分享 时间: 加入收藏 我要投稿 点赞

KEY:  Bloom's: Comprehension
 
     9.   “What is the project’s budget?” This is an example of a project’s _____ constraint.
 
ANS:  cost
 
PTS:   1                    DIF:    Difficulty: Easy                    REF:              p.8
OBJ:   LO: 1-2          NAT:  BUSPROG: Analytic            TOP:              What is a Product?
KEY:  Bloom's: Knowledge
 
   10.   The _____ of project management includes quality, scope, time, and cost constraints.
 
ANS:  quadruple constraint
 
PTS:   1                    DIF:    Difficulty: Easy                    REF:              p.9
OBJ:   LO: 1-2          NAT:  BUSPROG: Analytic            TOP:              What is a Project?
KEY:  Bloom's: Knowledge
 
   11.   _____ is “the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.”
 
ANS:  Project management
 
PTS:   1                    DIF:    Difficulty: Easy                    REF:              p.9
OBJ:   LO: 1-3          NAT:  BUSPROG: Technology                 
TOP:  What is Project Management?          KEY:  Bloom's: Knowledge              
 
   12.   Project management _____ describe the key competencies that project managers must develop.
 
ANS:  knowledge areas
 
PTS:   1                    DIF:    Difficulty: Easy                    REF:              p.11
OBJ:   LO: 1-3          NAT:  BUSPROG: Technology                 
TOP:  What is Project Management?          KEY:  Bloom's: Knowledge              
 
   13.   Project _____ management includes estimating how long it will take to complete work, develop an acceptable project schedule, and ensure timely completion of a project.
 
ANS:  time
 
PTS:   1                    DIF:    Difficulty: Moderate             REF:              p.11
OBJ:   LO: 1-3          NAT:  BUSPROG: Technology                 
TOP:  What is Project Management?          KEY:  Bloom's: Comprehension
 
   14.   Project _____ management consists of preparing and managing the budget for a project.
 
ANS:  cost
 
PTS:   1                    DIF:    Difficulty: Moderate             REF:              p.12