Information Technology Project Management 9th Edition by Kathy Schwalbe Test bank
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM
66. The term "_____" refers to work done in organizations to sustain the business.
ANSWER: Operations
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.4
QUESTION TYPE: Completion
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 5/13/2018 12:39 PM
67. _____ include people, hardware, software, or other assets.
ANSWER: Resources
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.7
QUESTION TYPE: Completion
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Legal - Legal
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM
68. A project’s sponsor is also known as a(n) _____.
ANSWER: primary customer
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.7
QUESTION TYPE: Completion
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM
69. In project management, the three limitations of scope, time, and cost are referred to as the _____.
ANSWER: triple constraint
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.7
QUESTION TYPE: Completion
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Legal - Legal
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM
70. The question, “What unique product, service, or result does the customer or sponsor expect from the project?” is an example of a(n) _____ constraint.
ANSWER: scope
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.7
QUESTION TYPE: Completion
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Comprehension
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 5/5/2018 6:04 PM
71. The question, “What is the project’s schedule?” is an example of a(n) _____ constraint.
ANSWER: time
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.7
QUESTION TYPE: Completion
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Product?
KEYWORDS: Bloom's: Comprehension
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM
72. “What is the project’s budget?” This is an example of a project’s _____ constraint.
ANSWER: cost
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.7
QUESTION TYPE: Completion
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Product?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM