Information Technology Project Management 9th Edition by Kathy Schwalbe Test bank

分享 时间: 加入收藏 我要投稿 点赞

 
73. The _____ of project management includes quality, scope, time, and cost constraints.
ANSWER:  quadruple constraint
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.9
QUESTION TYPE:  Completion
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  What is a Project?
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  4/27/2018 2:53 PM
 
74. _____ is “the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.”
ANSWER:  Project management
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.9
QUESTION TYPE:  Completion
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.3 - LO: 1-3
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  What is Project Management?
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  4/27/2018 2:53 PM
 
75. Project management _____ describe the key competencies that project managers must develop.
ANSWER:  knowledge areas
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.11
QUESTION TYPE:  Completion
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.3 - LO: 1-3
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  What is Project Management?
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  4/27/2018 2:53 PM
 
76. Project _____ management includes estimating how long it will take to complete the work, developing an acceptable project schedule, and ensuring timely completion of a project.
ANSWER:  schedule
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.11
QUESTION TYPE:  Completion
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.3 - LO: 1-3
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  What is Project Management?
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  5/5/2018 6:07 PM
 
77. Project _____ management consists of preparing and managing the budget for a project.
ANSWER:  cost
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.11
QUESTION TYPE:  Completion
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.3 - LO: 1-3
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  What is Project Management?
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  4/27/2018 2:53 PM
 
78. A(n) _____ is “a group of related projects, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits and control not available from managing them individually.”
ANSWER:  program
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.18
QUESTION TYPE:  Completion
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.4 - LO: 1-4
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension
TOPICS:  Program and Portfolio Management
KEYWORDS:  Bloom's: Knowledge
DATE CREATED:  4/27/2018 2:53 PM
DATE MODIFIED:  5/5/2018 6:10 PM
 
79. _____ refers to the process in which organizations group and manage projects and programs as a portfolio of investments that contribute to the entire enterprise’s success.
ANSWER:  Project portfolio management
POINTS:  1
DIFFICULTY:  Difficulty: Easy
REFERENCES:  p.19
QUESTION TYPE:  Completion
HAS VARIABLES:  False
LEARNING OBJECTIVES:  INFO.SCHW.14.4 - LO: 1-4
NATIONAL STANDARDS:  United States - BUSPROG: - Comprehension